|
|
Smith Creek Parkway
Client: North Carolina Department of Transportation Location: New Hanover, NC Start Date: July 2002 End Date: October 2005 Contract Amount: $42.8 million
The Smith Creek Parkway has been a priority project for the Wilmington
area since 1972. It needed improvement to alleviate traffic congestion
on I-40 and US-117, eliminate delays at several key intersections and
help North Carolina revitalize local businesses in the downtown area.
Balfour Beatty Infrastructure, Inc. began work on this project in 2002
to widen and extend the parkway, construct 10 bridges of which three
cross the creek and three more cross an existing railroad, add 6.7 lane
miles of roadway, demolish the existing bridge structure, and perform
the work in an environmentally sensitive area.
The
environmental issues were especially complex. Many studies since the
1970s have taken into account such issues as noise, abandoned landfill
sites and wetland incursion. Balfour Beatty Infrastructure worked
carefully to construct bridges over the pristine wetland areas, and to
ensure proper protection and care during the demolition of the old
bridge.
The North Carolina Department of Labor has recognized Balfour Beatty Infrastructure for its safe work practices at this project.
|