|
|
Dorchester Tunnel
Client: Massachusetts Water Authority Location: Boston, MA Start Date: August 2007 End Date: October 2009 Contract Value: $146 million
Balfour
Beatty Infrastructure, Inc. began work in August 2007 on the Dorchester
Tunnel in Boston, a $146 million job for the Massachusetts Water
Authority. The three-year project was a joint venture with M. L. Shank,
Co.
The work involved cutting an 11,000-foot tunnel to receive
storm water runoff that empties into a pump station. The
tunnel is
17 feet in diameter and is constructed of a series of four-foot rings
that create a watertight internal surface. The top of the tunnel lies
30 feet beneath the street.
A sophisticated cutting machine that
tunnels through various materials -- clay, sand, organic material,
gravel -- progressed at a rate of 48 feet per day during the
project’s two nine-hour daily shifts.
|